For the umpteenth time this year, the Transmission Company of Nigeria (TCN) on Sunday announced that vandals had again attacked the Gombe-Damaturu-Maiduguri 330kV transmission line.

The line has for over a year come under incessant attacks by terrorists in the North-east who had continued to destroy it after several repairs by the transmission company.

According to the company, the latest incident has not only thrown the entire Yobe state capital, Damaturu into total darkness, but had also impacted neighbouring Maiduguri in Borno state.

“The Transmission Company of Nigeria (TCN) hereby states that its tower No T372, along Gombe -Damaturu-Maiduguri 330kV transmission line was brought down by vandals on Saturday, 21st September 2024, at about 1:44am.

“This development has thrown the whole of Damaturu, the capital of Yobe State, up to Maiduguri in Borno State out of power supply.

“This time, the vandals cut off all four tower footing, resulting in the collapse of tower T372 along the Gombe-Damaturu-Maiduguri section, which was discovered by TCN’s linesmen deployed on emergency patrol.

“Following this destructive attack, effort is ongoing  by TCN’s engineers in the interim, to back feed Damaturu through a 33kV transmission line from Potiskum, while Maiduguri town will be fed from the Maiduguri Emergency Power Plant (MEPP),” the TCN stated in a statement signed by its General Manager, Public Affairs, Ndidi Mbah.

Meanwhile, the transmission company stated that work will commence immediately to dismantle and evacuate the collapsed tower for reconstruction and restoration of the transmission line.    

“TCN frowns at the incessant attack on our collective national assets and enjoin citizens to be vigilant in protecting these assets and also to report suspicious activities or persons around our transmission infrastructure to law enforcement agents or TCN offices in that vicinity .

“TCN is committed to a quick restoration of bulk power to the affected areas and will expedite reconstruction work on the tower to ensure that it is completed as soon as possible,” the commission added.

Emmanuel Addeh

Follow us on:

AriseNews

Recent Posts

Ongoing Oil Sector Sabotage Probe Stalled by House of Representatives’ Rules Compliance Issues

A strong indication emerged on Sunday that the ongoing probe into the sabotage in the…

7 mins ago

Zelensky to Present ‘Plan for Victory’ to President Biden During US Visit

Ukrainian President Volodymyr Zelensky is set to unveil his "plan for victory" during a visit…

58 mins ago

CBN’s MPC To Review Economic Outlook Amid Inflation, Naira Depreciation, Energy Crisis

The Monetary Policy Committee (MPC) of the Central Bank of Nigeria (CBN) will reconvene on…

60 mins ago

Nigeria Tops Global Food Insecurity List With 31.8 Million People Acutely Affected, Says WFP

No fewer than 31. 8 million people in Nigeria are acutely food insecure, the highest…

1 hour ago

Australia’s Consumer Watchdog Sues Supermarket Giants Over Misleading Price Claims

Australia’s two largest supermarket chains, Coles and Woolworths, are facing legal action from the Australian…

1 hour ago

Six Dead, 10 Missing as Record Rains Trigger Floods, Landslides in Japan

Record-breaking rainfall in Japan’s Ishikawa prefecture has resulted in devastating floods and landslides, leaving six…

1 hour ago